【单选题】7 / 22人工挖土:基本工作时间6 h6\,\mathrm{h}6h(即0.750.750.75工日/m3\mathrm{m}^3m3),辅助时间占工序作业时间2%2\%2%,准备与结束、不可避免中断、休息分别占工作日3%3\%3%、2%2\%2%、18%18\%18%。时间定额约为?A0.7650.7650.765工日/m3\mathrm{m}^3m3B0.9940.9940.994工日/m3\mathrm{m}^3m3正确C1.0061.0061.006工日/m3\mathrm{m}^3m3D0.7500.7500.750工日/m3\mathrm{m}^3m3参考答案B参考解析工序作业时间=0.75/(1−2%)=0.765=0.75/(1-2\%)=0.765=0.75/(1−2%)=0.765;时间定额=0.765/(1−23%)≈0.994=0.765/(1-23\%)\approx0.994=0.765/(1−23%)≈0.994工日/m3\mathrm{m}^3m3。